It is a hospital complex of considerable importance as it embraces the entire Domitio coast with a very high demand for beds. Inside it has been realized a new four-storey building with operating block, reanimation, etc. with the most advanced solutions and technologies on the market.
– realization of 1 operative block composed of three sterile operating rooms, 1 gypsum room, 2 sub-sterilizations, 3 preparation and awakening rooms. All made with air conditioning system with absolute air filtration
– construction of a gas-medicinal plant and related production and distribution plants
– Supply and installation of a UTA air treatment unit and two groups of refrigeration units for air conditioning through adjustable long-throw nozzles.
– Implementation of lighting system with remote control electronic systems and remote control with related data transmission systems realized with optical fiber; Photometric, radiometric and colorimetric measurement for interiors and exteriors as well as control for the protection of visual hygiene
– All the electrical, anti-intrusion, fire and air conditioning systems have been designed to be managed and controlled by supervision and remote management systems using hardware and software and tbx made in the field
– 20,000 KG of galvanized channels
– 20,000 ML of electric cables
– 8,000 sqm of stoneware flooring
– 4.000 MQ of vinyl sheet covering
– 3.000 MQ of internal partitions
– 1,000 MQ of PVC frames
– 1000 lighting bodies
– 600 square meters of static-dissipative rubber flooring
– average workforce employed about 20 workers assigned to the various tasks